Security Release Process

If a security fix release is required, run through the below steps.

Release Timeline

Notes:

  • All cut-off dates are based on 10am (San Francisco Time) on the day stated.
  • T-minus counts are measured in “working days” (weekdays other than major holidays concurrent in US and Canada) prior to release day.

A. (T-minus 4 working days) Code complete

  1. Release Manager:
    • Once the list of security issues to be fixed is finalized, post this checklist in Release Checklist channel
    • Notify community about upcoming security release through a Twitter announcement and in changelog with links to approved fixes and a date tagged as “TBD”
    • Email GitLab release team about upcoming security release.
    • Work with a developer to submit GitLab MR following this process and test the upgrade once the GitLab MR is merged and included in their RC.
    • Open a ticket to submit Gitlab Omnibus RC install of Mattermost
    • Make a post in Announcements channel announcing the security release to the rest of the team with links to approved tickets and include a link to the ticket to submit the GitLab MR
  2. Dev:
    • PRs for hotfixes are made to release branch
    • Review PRs made from release branch and merge changes into the release branch as required and merge the release branch back into master once per day

B. (T-minus 3 working days) Release Candidate Cut

  1. Build:
    • Verify with Release Manager before cutting any new dot release RCs (approved fixes should be merged)

C. (T-minus 2 working days) Release Candidate Testing

  1. QA:
    • If the dot release takes place during a regular release, update ci-linux-mysql-prev to dot-release RCs for the previous release and keep rctesting.reddogsofwar on the latest regular release version
    • Test the new RC to verify fixes merged to the release branch work
    • Post in Release Discussion channel after testing
  2. Logistics:
    • If the security researcher has not previously received a security researcher mug, order one for them

D. (T-minus 0 working days) Release Build Cut

Once security fix release is ready to cut:

  1. Dev:
    • Tag a new release (e.g. 1.1.1) and run an official build
    • Verify hashes and GPG signatures are correct, once build is cut
    • Delete RCs after final version is shipped
  2. Release Manager:
    • Update the changelog
    • Update the version archive
    • Update Mattermost server download page with the links to the EE and TE bits
    • Test the download links before and after updating the page
    • Contact owners of community installers or submit PRs to update install version number
      • For Puppet, Heroku and Ansible Playbook, post to Installers and Images channel announcing the new release. See example.
      • For Chef Cookbook, open a new issue to announce the new release. See example.
      • For Yunohost, open a new pull request to update the version. See example.
      • For OpenShift, open a new pull request to update the version. See example.
    • Update Security Research Hall of Fame on the Responsible Disclosure Policy page
    • Post Mattermost Security Updates 30 days after the dot release has shipped
      • Update Security Issues spreadsheet with issue number from posted update (e.g. v3.2.0.1)
  3. Marketing: